The ambitious Raipur–Visakhapatnam Economic Corridor, being developed under the Bharatmala Pariyojana, has come under scrutiny following reports of sinking bridges, cracked road surfaces and construction delays.
The concerns were highlighted in a report published by Swarajya on November 29, 2026, raising questions about the construction quality and execution of the major highway project.
A major connectivity project
The Raipur–Visakhapatnam Economic Corridor is a proposed 464–465 km six-lane, access-controlled greenfield highway connecting Abhanpur near Raipur in Chhattisgarh with Sabbavaram near Visakhapatnam in Andhra Pradesh through Odisha.
The project has an estimated investment of approximately ₹16,491 crore, according to the Ministry of Road Transport and Highways.
Once completed, the corridor is expected to improve connectivity between central India and Visakhapatnam Port, supporting passenger movement, freight transportation and regional economic activity.
Construction delays and infrastructure concerns
The latest report highlights several alleged infrastructure problems along the corridor, including:
-
Bridges reportedly showing signs of sinking.
-
Cracks appearing on certain road sections.
-
Delays affecting construction progress.
-
Concerns about the quality and durability of infrastructure.
These reported issues have brought attention to the need for proper construction supervision, quality inspections and timely corrective measures.
Previous delays recorded in official documents
Construction delays have also been acknowledged in official parliamentary records.
In an August 2025 reply, the Ministry of Road Transport and Highways reported that a 24.30 km section of the Andhra Pradesh package had faced delays because of fly ash supply issues, mining permissions, land acquisition and the shifting of 400 kV electricity lines.
At that time, 24.025 km had been completed, with the remaining 0.275 km pending because of land acquisition issues.
What does this mean for Visakhapatnam?
The corridor is expected to strengthen Visakhapatnam's connectivity with Raipur and several industrial and mineral-producing regions across Chhattisgarh and Odisha.
The project is also expected to reduce the distance between Raipur and Visakhapatnam and improve access to the city's port and industrial facilities.
However, reported infrastructure concerns underline the importance of ensuring construction quality and road safety before the highway becomes operational.
The project's long-term benefits will depend not only on completing the highway but also on ensuring that its bridges, roads and other structures meet the required engineering and safety standards.
Team Hello Vizag