Visakhapatnam Railway Station to Have 14 Platforms, Targeting Top Five Nationally



Railway Station Expansion to 14 Platforms

Visakhapatnam Railway Station is undergoing a major redevelopment, with plans to increase the number of platforms from eight to 14.

Visakhapatnam MP M. Sribharat shared the update on November 19 after inspecting the ongoing redevelopment works along with railway officials. He said the Railway Board had approved the proposal to add six platforms, which would place Visakhapatnam among the five major railway stations in India with the highest number of platforms.


Project Cost Increased to ₹660 Crore

The redevelopment project was initially estimated at ₹480 crore. According to the MP, the project cost has now been increased to ₹660 crore, taking into account rising passenger traffic and the city's future transportation requirements.

The expansion is intended to improve passenger movement, increase train-handling capacity and address operational constraints at the station.

Airport-Style Air Concourse and Parking Facilities

A 72-metre-wide air concourse is being constructed to connect the new station buildings on either side. Designed along the lines of a modern airport terminal, the facility is expected to accommodate approximately 4,000 passengers at a time.

The redevelopment also includes parking facilities for around 450 cars and 2,000 two-wheelers, along with dedicated pick-up and drop-off spaces for cab aggregators.

Railway Line Expansion to Improve Train Operations

Quadrupling works are underway on the existing two railway lines between Gopalapatnam and Visakhapatnam. The expansion is intended to increase rail capacity and reduce delays in train arrivals and departures.

The MP also highlighted the need for sustainable infrastructure, including rainwater harvesting and sewage treatment facilities across the station premises.

Completion Targets for 2027 and 2028

The redevelopment is being implemented in phases. The first phase is targeted for completion by December 2027, while the overall project is expected to be completed by December 2028.

Once completed, the expanded station is expected to provide additional platform capacity, improved passenger facilities and better operational efficiency for one of Andhra Pradesh's busiest railway hubs.


Port Workers’ Unions Oppose Privatisation of Visakhapatnam Port Hospital, Announce Protest Read Previous

Port Workers’ Unions Oppose Privatisation of Visakhapatnam Port Hospital, Announce Protest

Visakhapatnam, Tirupati and Amaravati Economic Regions to Shape Andhra Pradesh’s Development Read Next

Visakhapatnam, Tirupati and Amaravati Economic Regions to Shape Andhra Pradesh’s Development

Sign up for the Newsletter

Join our newsletter and get updates in your inbox. We won’t spam you and we respect your privacy.